SPHS Construction Update - October 25, 2012

Area F - Over the past month steel erection, exterior sheathing and roofing has been on-going in the Cafeteria, and Lecture Hall areas.  Interior metal stud partition framing, plumbing and HVAC piping are continuing. Windows will begin to be installed over the next few weeks.

Area A and B - Foundation work is continuning in the classroom wing behind Beal Gym and the Main Office entrance areas.  Structural steel erection and concrete slab work will begin during November in these areas.

Unitil installation of the permanent gas line is nearing completion.  Temporary heating has been established to all parts of the building.

Underground mechanical and plumbing piping throughout the site is continuing.

Please enjoy the latest pictures of the project during the month of October.

 

 

If you need assistance with translation of this document, please contact Instructional Support at 871-0555.

Si desea que esta traducida, por favor comuníquese con la oficina de Apoyo Educativo en el 871-0555.

Nếu bạn muốn có này dịch, xin vui lòng liên hệ với văn phòng hỗ trợ giảng dạy tại 871-0555.

Hadii aad dooneysid in laguu tarjumo fadlan la soo xiriir Xafiiska caawinta wax barasho ee telefoonkeedu yahay 871-0555