SPHS Construction Update

October 11, 2012 Construction Update:

 

The practice fields have been built and were seeded during September. Grass is just beginning to grow.

Utilities to the Quarterback Club were reconnected.

Additional crews are in place to work on foundations in the new classroom wing behind Beal Gym.

Base preparation and binder course paving has been laid for the roadway, back parking lot and tennis courts.

Temporary natural gas connection has been installed to the converted temporary boilers.

The focus has been on getting site work completed for winter.

 

Planned activities for October:

 

Complete steel erection, exterior sheathing and start roofing in the Cafeteria, and Lecture Hall areas.

Unitil installation of the permanent gas line is to be completed.

Continue with concrete foundations, slabs and backfilling in the Learning Commons, Classroom and Locker Room areas connecting the Cafeteria/Lecture Hall to behind Beal Gym.

Continue underground mechanical and plumbing piping.

The concrete floor of the Lecture Hall will be completed

Roofing and Insulation will begin in the Cafeteria and Lecture Hall areas.

If you need assistance with translation of this document, please contact Instructional Support at 871-0555.

Si desea que esta traducida, por favor comuníquese con la oficina de Apoyo Educativo en el 871-0555.

Nếu bạn muốn có này dịch, xin vui lòng liên hệ với văn phòng hỗ trợ giảng dạy tại 871-0555.

Hadii aad dooneysid in laguu tarjumo fadlan la soo xiriir Xafiiska caawinta wax barasho ee telefoonkeedu yahay 871-0555