Week of 6/4/12
-
Depending on the blasting permit approval more than likely blasting will start on Monday/Tuesday and will be ongoing all week. At times it may only be a couple times during the day, in other cases smaller shots within an hour of each other. ( 3 Horns = 5 min. to blast, 2 Horns = 1 min. to blast, 1 Horn = all clear)
-
Site excavation and parking lot backfill will continue this week.
-
CMP is anticipated to install the new pole on . A crew will mobilize to install the underground in preparation of the cut over anticipated within the next few weeks.
-
Around the middle of the week PC Construction will need to access the lawn area on the South side of Beal Gym to identify if the old steam lines need to be abated. They will coordinate with the Abatement Contractor. This will be done after school hours.
-
Inside the building, work on installation of the fire pump feed and temporary power on the first floor of the existing building and ground floor of Beal Gym will proceed as much as possible without causing unnecessary disruption.